The time to do a piece of work is inversely proportional to the number of men employed. If it takes 4 men to do a piece of work in 5days,how long will it take 25 men?
2 Answers
Jul 6, 2018
Explanation:
"let t represent time and n the number of men"
"the initial statement is "tprop1/n
"to convert to an equation multiply by k the constant"
"of variation"
t=kxx1/n=k/n
"to find k use the given condition"
t=5" when "n=4
t=k/nrArrk=tn=5xx4=20
"equation is "t=20/n
"when "n=25
t=20/25=4/5" day"=19.2" hours"
color(white)(xxxxxxxxxxxx)=19" hours and "12" minutes"
Jul 6, 2018
Let
Inverse variation can be modeled by:
Given that in 5 days, 4 men can complete work:
To solve for time, when 25 men work: